Hampton & Kempton Park Dosing Kiosks

Design, supply and installation of 16 new dosing kiosks across Kempton and Hampton WTWs for Thames Water, delivered as a complete M&E package from inception through to commissioning.
Client:
CAB JV
Site Owner:
Thames Water
Location:
Middlesex
Value:
£900,880
Date:
February 2022 – January 2023

Challenge

During the Kempton Slow Sand Filter M&E refurbishment, an additional requirement was identified to design and install the Mechanical & Electrical installation for a new dosing kiosk per filter bed (12 at Kempton WTW and 4 at Hampton WTW).

Scope

The project entailed the design, supply and installation of dosing kiosks, low voltage cable, instrumentation, pumps, valves, and associated pipework and dosing equipment.

Solution

FSD provided design development and support, plus project management and administration. This office support, combined with previous project on-site experience, meant that FSD could work with all project stakeholders to expedite delivery. FSD developed this scheme from inception, through concept and detailed design, off-site build, on-site installation, into commissioning and being put into service.

Outcome

It was particularly challenging to maintain project progress due to global supply issues, but using FSD’s supply partners, alternative sources provided the required parts so that programme expectations were met.

Latest Project

Otterbourne WSW Upgrade

£2.8m electrical contract as part of a £60m scheme to upgrade Otterbourne WSW for Southern Water, including HV/LV systems, instrumentation, building services and design development across multiple treatment areas.

Ready to discuss your next project?

Whether you need complete M&E design and installation, specialist pipework fabrication, or HV/LV electrical systems, our experienced team is ready to help. Get in touch to discuss your requirements.